PT. X is one of the companies located in Dumai Industrial Region, produces fertilizer. This company has three production plants. The production capacity of the first plant is 450 tons/day, the second plant produces 750 tons/day and the third plant produces 700 tons/day.  PT. X is supported by 2 sub companies, they are PT. A and PT. B. PT. A operates 5 bagging lines and PT. B operates 3 bagging lines. The fertilizer bagging process has three steps where each step has its own work station: putting the labeled sack to the hook followed by filling the sack with fertilizer, installing the tie cable, and sewing the fertilizer filled sack. From the initial survey, it was found that the processing time is not optimal to reach production target. PT. A and B have to set 24 working hours per day to run the target resulting on frequent over time, excessive fatigue and the negative impact of physically and mentally for the workers. Author’s hypothesis is the current condition has been one of the reasons for a decline of the production output. Therefore, the purposes of the research are to find the impact of current working hours and shift work pattern on the physical and psychological response of the workers and to calculate the standard time required to complete one cycle of bagging process. This standard time is very crucial to determine production target thus determine the optimal working hours and shift rotation.

Measuring of heart rate are collecting results of a questionnaire of NASA-TLX are the parameters used to evaluate the physical and psychological response of workers. Two workers from different group worker, different shift work, from PT. A and PT. B were selected as samples to evaluate their heart rate pattern. The questioner spread out to all workers. Time standard was determined by observing and taking data of   40 bagging cycles for each shift work.

The results show that shift work affecting the physiological response of workers in PT. B in the category between moderate to extreme especially for working element of arranging fertilizer sack to the pallet. This result was found for the two group workers. Frequent short rests between times are required to provide quick recovery for the workers and reduce excessive fatigue. Average standard time complete one bagging cycle was 0.12 minutes and 0.13 minutes for PT. A and PT. B, respectively. These standard times can be used to set the production output target for the two companies. Last, short rotation shift work with an additional number of workers is recommended for the shift pattern.

Downloads

Download data is not yet available.

References

[1] Elfrida. (2009). Penilaian dan Perbaikan system kerja dengan Macro ergonomic organizational.USU. Medan.

[2] Demerouti E, Sabine A, Geurts E, Bakker A b and Euwema, M. (2004). The impact of shiftwork on work, home conflict, job attitudes and health, Ergonomic, Volume 47 No 9 (987-1002).

[3] Kimberly, F.K, 2011. Pengaruh Shift Kerja Terhadap Kelelahan Pekerja pabrik Kelapa Sawit. Fakultas Teknik. Universitas Al Azhar Medan.

[4] Salma, U. and Rao K. K. (2014). Shift work and Depression, 4 (4), 417-422, International Journal of Environmental Research and Development.

[5] Sutalaksana, I.Z., Anggawisastra, R., Tjakraatmadja, J.H. (2006). Teknik Perancangan Sistem Kerja, Edisi Kedua, ITB, Bandung.

[6] Wignjosoebroto, S. (2008). Ergonomi Studi Gerak dan Waktu, Teknik Analisis untuk Peningkatan Produktivitas Kerja, Edisi Pertama, Cetakan Keempat, Guna Widya, Surabaya.

[7] Kroemer K H E, Kroemer H J, Kroemer K E and Elbert. (2010). Engineering Physiology, Edisi ke 4, Springer Verlag berlin Heidelberg.

[8] Knauth, P. (1988), The Design of Shift Systems, International Journal of Industrial Ergonomic, Vol 3

[9] Nurmianto, E. (2004).Ergonomi Konsep Dasar dan Aplikasinya. Penerbit Guna Widya. Edisi Kedua. Surabaya

[10] Manuaba, A. (2010).Ergonomi, Kesehatan dan Keselamatan Kerja. Editor: Sritomo W dan Stefanus E.W. Proceeding Seminar Nasional Ergonomi. Penerbit Guna Widya. Surabaya.

[11] Tayyari F and Smith J. L. (1997).Occupational Ergonomics Principle And Application. Hapman & Hall (London)

[12] Santoso, D.A., Supriyadi, A. (2010). Perhittungan Waktu Baku dengan Metode Work Sampling untuk Menentukan Jumlah Tenaga Kerja Optimal, Prosiding Seminar Nasional Sains dan Teknologi, Fakultas Teknik Uniersitas Wahid Hasyim Semarang, c1-c4.

[13] Noor, I. (2011). Analisa Penentuan Waktu Baku untuk Mempersingkat Proses Pelayanan Bongkar Muat di Pelabuhan Trisakti Banjarmansin, Jurnal INTEKNA, Tahun XI, No. 2, 171-177.

[14] Walangitan, R. (2012). Produktivitas Tenaga Kerja dengan Menggunakan Metode Work Sampling pada Pekerjaan Kolom dan Balok Mega Trade Center Manado, TEKNO-SIPIL, Volume 10, N0.57.

[15] Rinawati, D.I., Puspitasi, D., Muljadi, F. (2012). Penentuan Waktu Standar dan Jumlah Tenaga Kerja Optimal pada Produksi Batik Cap (Studi Kasus: IKM Batik Saud Effendy, Laweyan), JATI Undip, Vol II, No 3.

[16] Rizani, N.C., Safitri, D.M., Wulandari, P. A. (2013). Perbandingan Pengukuran Waktu Baku dengan Metode Stopwatch Time Study dan Metode Ready Work Factor (RWF) pada Departemen Hand Insert PT. Sharp Indonesia, Jurnal Teknik Industri, ISSN:1411-6340, pp 127-136.

[17] Barnes, F.J., Kimberley, D.S, Alyssa, M., Benjamin, W. (2008). What Aspects of Shiftwork Influence off-shift well-being of Healthcare Workers?, Applied Ergonomis Journals 39:586-596. Elsevier, USA

[18] Ramdan, I. (2007). Dampak Giliran Kerja, Suhu dan Kebisingan terhadap Perasaan Kelelahan Kerja di PT LJP Provinsi Kalimantan Timur, The Indonesian Journal of Public Health,4(1): 8-13

[19] Taufik I dan Salami I R . (2012). Hubungan Antara Shift Kerja Dengan Tingkatan Kelelahan Kerja Pada Pekerja Di Pabrik Perakitan Mobil Indonesia. Teknik Lingkungan ITB, Bandung.

[20] Asare D, Sebiawu G E, and Mensah N J. (2013). Fatique Management Among Mining Departement Shift Workers At Newmont Ghana Gold Limited Ahafo Mine, Kenyase, Brong Ahafo Region, Ghana, International Journal Of Scentific & technology Research , Volume 2 (10).